Sponsored Programs
Proposal Preparation / Submission
Guidelines for Proposing Cost Sharing
Background
As a recipient of Federal funds, when making cost sharing/matching commitments,
UCR must propose the cost sharing in a manner consistent and in accordance with
federal regulations.
Definitions
- Cost sharing (also called matching) is any portion of the total
costs of a project or program not borne by the sponsor. Cost sharing typically takes
the form of in-kind resources (e.g., contributed project personnel effort) or cash.
- Cost sharing commitment means any cost sharing that is offered
and quantified anywhere in a proposal.
- Cost sharing contribution means the use or expenditure of any in-kind
resource or cash to fulfill a cost sharing commitment in the course of performing
the scope of work under an extramural award.
Back to top
Proposing Cost Sharing Commitments
If cost sharing is quantified in any part of a proposal that has been submitted
to an extramural sponsor, a cost sharing commitment has been made and the administering
department/unit is responsible for fulfilling the commitment in the event that the
sponsor makes an award.
Cost sharing is considered quantified when UCR records, in conjunction with information
contained in a proposal, are sufficient to calculate the amount of the cost sharing
commitment. For example, if a proposal states that a researcher will contribute
10% of her time to a project during the first budget period, but her salary will
not be charged to the award, then UCR has committed to cost share the dollar amount
equal to 10% of the researcher's salary, plus associated fringe benefits. The dollar
amount of the researcher's salary for the first budget period can be calculated
using the information contained in the proposal, as well as payroll and personnel
documents available to UCR.
Principal investigators and departments should refrain from making cost sharing
commitments unless cost sharing is required by the sponsor or necessary to ensure
the competitiveness of a proposal. Sposnors treat cost sharing as an eligibility
requirement, not a merit review requirement. Thus, offering cost sharing in the
absense of a sponsor's programmatic requirement to cost sharing does not enhance
the competiveness of a proposal unless the following circumstances are present:
- The sponsor's program guidelines limit the maximum amout of funding (i.e., awards
may not exceed a specific dollar figure); and
- The total estimated project costs (direct and F&A) will exceed the sponsor's
maximum funding per award
In such cases, cost sharing the difference between the total estimated project costs
and the maximum award amount allowed by the sponsor does enhance the competitiveness
of the proposal.
Cost sharing commitments involve increased administrative burden (associated with
tracking/reporting shared costs) and are subject to audit. Consequently, principal
investigators, chairs, directors, deans and other UCR officials should carefully
consider the cost effectiveness and the expected benefits of each cost sharing commitment
prior to making such an offer.
Occasionally, the competitive nature of a funding opportunity may necessitate describing
resources that are not eligible, allowed or offered as cost sharing, but will be
made available to the proposed project/program. In such cases, these resources may
be described as "resources available at no direct cost to the project" or "resources
that will benefit the project". In addition, the proposal should not indicate or
disclose the dollar value of any such resources. Examples of such resources include,
but are not limited to:
- Equipment in the possession of UCR at the time a proposal is submitted to a sponsor
or that will be in the possession of UCR prior to the effective date of an award;
- UCR-owned space; and
- Time and effort of collaborators serving solely in an advisory or mentoring capacity.
Back to top
Cost Sharing on Contract Proposals
Because of the procurement nature of contracts, especially federal contracts, cost
sharing commitments should not be made or offered in proposals that will lead to
contract awards. However, it may be appropriate to make cost sharing commitments
in proposals that will result in another institution issuing a subaward (e.g., subagreements,
subgrants or subcontracts) to UCR where the prime award is a grant or cooperative
agreement.
Proposing Project Personnel Effort (UCR-paid Salaries/Fringe Benefits) as Cost Sharing
UCR policy permits faculty members to devote a reasonable portion of their UCR-paid
time and effort to accomplish their research projects. Therefore, the most appropriate
cost sharing commitments/contributions are UCR-paid salaries and fringe benefits
of faculty directly engaged in the project.
When offering project personnel effort as cost sharing, the proposed level of effort
must be realistic (i.e., neither overstated nor understated) and reasonable (i.e.,
total percent of effort devoted to all sponsored programs and other UCR-related
duties does not exceed 100%). In determining the appropriate level of cost shared
effort, principal investigators must consider the following:
- the sponsor's requirement for cost sharing;
- the percentage of time spent on other sponsored programs;
- the amount of effort devoted to other functions such as teaching and public service;
and
- the size of the project.
Back to top
UCR Personnel as Collaborators
It is important to remember that quantifying UCR personnel effort anywhere in a
proposal constitutes a cost sharing commitment. Therefore, if a project involves
UCR personnel acting as collaborators, where such collaborators are serving solely
in an advisory or mentoring capacity and the department/unit does not intend to
offer the collaborator's personnel costs as cost sharing, then the collaborator's
effort should not be quantified.
Back to top
Eligibility Criteria for Shared Costs
The following eligibility criteria apply to all costs proposed (and ultimately accounted
for) as cost sharing:
- The costs must be able to be documented and verified based on UCR's records;
- The costs must not be included as a cost sharing commitment related to any other
project or program (i.e., the same costs may not be proposed as cost sharing for
two or more projects);
- The costs may not be committed, or contributed, from another extramural award, except
where specifically authorized by Federal statute or the sponsor (i.e., costs incurred
under a NIH grant may not be proposed or accounted for as a cost sharing contribution
under a NSF grant or any other federal or non-federal grant);
- The costs must be necessary and directly related to the project objectives;
- The costs must be incurred during the same performance period as the award supporting
the project;
- The costs must be allowable and allocable under federal cost principles (OMB Circular
A-21) and the terms of the sponsored agreement; and
- The costs must be identified in the approved budget or award (either directly or
incorporated by reference) when required by the sponsor
Back to top
Costs Generally Allowed as Cost Sharing
- The effort of the principal investigator and project personnel devoted to the performance
of an award, in the form of contributed salary, wages and fringe benefit costs;
- The acquisition cost of equipment necessary for the successful completion of the
project;
- Laboratory and project supplies necessary for the successful completion of the project;
- Travel necessary for the successful completion of the project or for the purpose
of reporting research results;
- Other direct costs necessary for the successful completion of the project (e.g.,
purchased services, alterations or renovations necessary to conduct the project,
equipment maintenance, the cost of setting up equipment necessary for the successful
completion of the project);
- Facilities & Administrative costs associated with the direct cost elements proposed
as cost sharing; and
- Third-party contributions
Back to top
Costs Generally Not Allowed as Cost Sharing
- Administrative salaries, services and supplies, except when such costs will be incurred
in the performance of a non-Federal award, or where special purpose or circumstances
exist, which would allow for treating such costs as direct costs in accordance with
OMB Circular A-21;
- Salary costs above a regulatory cap (e.g., National Institutes of Health salary
rate cap);
- General purpose equipment;
- Equipment in the possession of the University at the time a proposal is submitted
to a sponsor or that will be in the possession of the University prior to the effective
date of an award;
- Unallowable costs as defined in OMB Circular A-21, section J; and
- UCR facilities.
Back to top